When does my project
get a final consistency determination?
A final consistency determination is issued when you and the project reviewers
concur with the proposed determination, including the stipulations. The final
consistency determination must be issued by the review deadline, generally 50
days.
When do I get my permits?
Once the final consistency determination is completed, most state agencies issue
state permits covered by the determination within five days. However, an agency
may find that additional time is necessary to fulfill its statutory requirements.
For example, leases and other disposals of state land or resources issued by
DNR generally require additional time. DCOM or the permitting agency can provide
you with more information on when you can expect to receive the permits for your
project.
|